A WATCHDOG that monitors safety in the nuclear industry is taken enforcement action against bosses at Sizewell A.

It follows an incident in September last year when 13,000 litres of treated pond water leaked from a waste treatment plant, known as an active effluent treatment plant (AETP).

The Office for Nuclear Regulation (ONR) is now taking enforcement action against Magnox Ltd, which is the licensee for the decommissioning power station.

The watchdog has also written to the station director to set out the actions that it expects to see happen.

This includes completing a long term review of the vulnerabilities at Sizewell A’s AETP and providing a copy of this review to the ONR, drawing up improvements to ensure that the risk is minimised to levels that are as low as reasonably practicable and providing the ONR with a commitment to share learning from this event with the rest of the Magnox fleet of reactors.

The watchdog also want to see a suitably prioritised and timed plan in which to make the changes and to be kept up to date with progress at appropriate intervals.


If you value what this story gives you, please consider supporting the Lowestoft Journal. Click the link in the yellow box below for details.

Become a supporter

This newspaper has been a central part of community life for many years, through good times and bad, serving as your advocate and trusted source of local information. Our industry is facing testing times, which is why I’m asking for your support. Every single contribution will help us continue to produce award-winning local journalism that makes a measurable difference to our community.

Thank you.

Most Read

Most Read

Latest from the Lowestoft Journal